Jump to: main content, navigation, or top of page.

Jump to: main content, navigation, or top of page.

Progress Casting Group

Customer
Progress Casting Group (Plymouth, MN)
Industry
Manufacturing
Demand
4,000 kW
Utility
Xcel Energy
Contract Signed
April 30, 2003
Testing Completed
June 13, 2003

Progress Casting had reliability issues with their utility as various construction projects in their area had contributed to multiple power outages over the previous 12 months. The lack of reliable power was affecting their productivity and their bottom line. Aware of the benefits that onsite generation could provide, Progress Casting came to Energy Alternative to design and manage their generator project. They decided to hire experts rather than tie up their personnel to manage a project of this type.

Working within a very short window of opportunity (less than 60 days), EA worked with their preferred vendors to procure equipment while ensuring their design met all utility and city requirements. Progress Castings has very sensitive equipment in their building so EA had to ensure a seamless transfer from utility to generator. EA also structured a financing package such that Progress Castings could pay for the generator out of their operating budget rather than their capital budget. EA even worked with the utility to maximize the rate savings to Progress Casting under the utility's Peak Control Rate Program.

Energy Alternative used their design expertise, buying power, and knowledge of utility requirements to commission this project in less than 90 days. As a result, Progress Castings no longer needs to worry about the utility adversely affecting their production. They can continue to do what they do best – manufacture quality parts for their customers.

Progress Castings looked around for other suppliers and found that EA provided the most extensive array of services and overall best value.

Our whole project was handled by Energy Alternative. They did a very good job. I spent about three years doing a lot of research, and I highly recommend Energy Alternative. All they do is generator installations.

Dana St. John
Plant Engineer
Progress Castings

Newsletter Sign up

The email address you wish to subscribe with.

Clients

  • Retail Chains
  • E-Commerce Centers
  • Food Distribution Centers
  • Telecommunication Centers
  • Education Facilities
  • Zoos

Testimonials

"EA coordinated a substantial distribution system modification within our plant and also designed and installed a 4 MW generation system. They worked with our utility and completed the project with minimum interruption."

Joe Tappanier
Plant Electrical Engineer
Gopher Resource Corporation

Jump to: main content, navigation, or top of page.

Document Information

Powered by WebleaseUSA.

Jump to: main content, navigation, or top of page.